Wednesday, January 5, 2011

Man Hole (Service Hole)

Alot of people put the man hole in the walk in robe? So every time a tradie goes to the roof cavity to fix something your cloths will be all dirty...etc. So we moved ours into the bathroom....plenty of room to put a ladder.

Blackbutt Timber floors

We will be having Blackbutt Timber floors on the bottom level.



Garage Door & Rain Water Tank

Our garage door & rain water tank


Painters have started

23nd Dec 2010 - the painters started just before christmas and should be complete by the 7th Jan 2011.





Tilers

5th Dec 2010 - the tilers started on all the wet areas




Wednesday, December 1, 2010

Kitchen & Bathroom & Doors & Stairs

1st Dec 2010 > A busy 2-3 weeks...waterproofing was done in the wet areas. The stairs was installed. Kitchen cupboards and benchtop was installed and currently they are installing all doors and door frames. Tiling should start next week...as the cement and sand has been delivered today.

We upgraded the kitchen sink so it is big enough to wash big pots and woks. Love our bench top


Don't really like the basin..but can live with it.



They still need to install the bulk head above the kitchen cupboards

Lockup

17th Nov 2010....Woohooo we have lockup !! That means the external doors are all installed and the place is lockup,