1st Dec 2010 > A busy 2-3 weeks...waterproofing was done in the wet areas. The stairs was installed. Kitchen cupboards and benchtop was installed and currently they are installing all doors and door frames. Tiling should start next week...as the cement and sand has been delivered today.
We upgraded the kitchen sink so it is big enough to wash big pots and woks. Love our bench top
Don't really like the basin..but can live with it.
They still need to install the bulk head above the kitchen cupboards
Our pictorial journey as we tackle the excitements and obstacles of building our Cosy Igloo
Wednesday, December 1, 2010
Lockup
17th Nov 2010....Woohooo we have lockup !! That means the external doors are all installed and the place is lockup,
Tuesday, November 9, 2010
Igloo Insulation
9th Nov 2010 - I went over to the Igloo on Sunday afternoon to take photographs of every single wall, ceiling....etc so we will have a records of where everything is behind the walls once everything is covered up. The insulation guys come today installing all the wall and ceiling insulation batts.
Wednesday, November 3, 2010
Cabling - Audio Visual | TV | Network | Alarm | Antenna
3rd November 2010 - the cabling guy is on site today installing all the cables for AV, TV, Network and Alarm system and also the antenna. I will be taking some pictures of all the walls once he is all done.
I notice the carpenters has leveled all the walls in the house, via halve cutting the frame and adding extra timbers. I notice one of the steel beams are not aligned :-( it has bricks around it and it is bolted to another steel beam...so I dont think we can fix it. Will have a chat to site boss.
I notice the carpenters has leveled all the walls in the house, via halve cutting the frame and adding extra timbers. I notice one of the steel beams are not aligned :-( it has bricks around it and it is bolted to another steel beam...so I dont think we can fix it. Will have a chat to site boss.
Tuesday, November 2, 2010
Electric Wiring | Carpenters | Frame Inspection
November 2nd 2010. It as been a busy few days. The Carpenters was in today fixing up all the internal woodwork and door frames. The also finish the fascia at the bottom front of house. I just drove by and had a look inside the house and notice ALL the electrical wiring was done....not sure when they did that.
We also had a frame inspection today...organised by the builders.
We also had a frame inspection today...organised by the builders.
Friday, October 29, 2010
Roof Tilers are back
Thursday 28th Oct 2010 - the roof tilers are back working on the lower front, back and side roof. The did not turn up today to finish the job :-(
Tuesday, October 19, 2010
Roof scaffolds down and bricks cleaned
19th Oct 2010 - A different team came onsite today to remove roof scaffolds and put back the roof tiles where the scaffold was mounted. Also the brick cleaner was in again cleaning the bottom level and also the inside bricks of the garage.
Friday, October 15, 2010
Eaves Painted and Scaffolds moved down
15th Oct 2010 - The scaffolders are in this morning removing all the scaffolds to ground level so the roof guys can install the alfresco roof. The top roof capping (13th Oct) was all complete and the eaves plus the top downpipes was also painted (14th Oct).
Monday, October 11, 2010
Roof Eaves
Monday 11th Oct 2010 > Top roof is complete just waiting for them too cement down the roof cappings. Hopefully they will start on the lower back roof soon. The carpenters was in today installing the top Roof eaves...all done in one day
Tuesday, October 5, 2010
Timber Flooring
Finally we had some time on the long weekend to look at some timber flooring...still undecided, but we are most likely going with a yellow tone timber...something that is cool and fresh and also it will make the house brighter. A good idea is to look at houses online that is for sale and has the timber floor species you want, it was hard just looking at a patch of timber at the display showrooms.
There are working on our igloo roof
Tuesday 5th Oct 2010 - The roof tilers have started today after the gutters was installed on Saturday 2nd Oct. Sarking will go on first before the roof tiles.
Monday, September 27, 2010
Thursday, September 9, 2010
Bricks - 2nd level
The brickies came back on the 31st August 2010, a week after the scaffolding was put up. They will stay until the job is complete. It is a small team of the Master and his 2 Assistants.
Friday, August 20, 2010
Bricks - more ice bricks + scaffolding
The scaffolding was completed on Thursday 19th August 2010. The plumbers also turned up in the arvo to do some more work on the 2nd level.
More bricks arrived this morning, hopefully the brickies will start next week.....
update - this arvo all the bricks was moved inside the fence :) lucky they did that or on Monday most of it will not be there...
More bricks arrived this morning, hopefully the brickies will start next week.....
update - this arvo all the bricks was moved inside the fence :) lucky they did that or on Monday most of it will not be there...
Monday, August 16, 2010
Bricks - ground level complete
Woohooo, just talked to the brickies this morning, the ground level bricks will be completed today and the scaffolding will be put up this Thursday and the top story bricks will be layed....
Thursday, August 12, 2010
Bricks - front of igloo
The bricks are up at the front of four igloo. Abit more bricks to go around the garage and the scaffolding team with come and prep the whole house before the brick layer comes back to start the 2nd story.
Thursday, August 5, 2010
Bricks & Pipes
Thursday 5th August 2010 - I though it is time to take some pics of the gas and water pipes locations before the bricks go up and cover it all. Just for future reference so i know where all the pipes are. I did the same thing with all the drain pipes underground
Gas + Water pipes
A one man brickie...he is doing the whole house...which i think is awesome
The back alfresco is taking shape
Gas + Water pipes
A one man brickie...he is doing the whole house...which i think is awesome
The back alfresco is taking shape
Wednesday, August 4, 2010
Brick Layers have started
Monday 2nd August 2010 - Last week our site supervisor said there was a shortage of brick layers and the wait will be at least 4 weeks :( However on Monday he said he found a brickie that can start on our Igloo...very happy :-)
Looking good - the alfresco area, you can see the drain for the outdoor sink
Looking good - the alfresco area, you can see the drain for the outdoor sink
Friday, July 23, 2010
Monday, July 19, 2010
Saturday, July 17, 2010
Friday, July 16, 2010
Monday, July 12, 2010
Friday, July 9, 2010
Wednesday, July 7, 2010
Tuesday, June 22, 2010
Demolition
23rd March 2010 - It was sad seeing our Igloo getting demolished :(
Five days later, our nice level land
Five days later, our nice level land
The "old" Igloo
After living in our "Old" Igloo for over 12 years we have out grown it with new additions to the family.
Monday, June 21, 2010
Sunday, June 20, 2010
The journey begins....
Welcome to our Cozy Igloo :-) This blog will feature all the excitements and obstacles of building our Cosy Igloo.We will be building the Manhattan 37 from Masterton Homes.
Subscribe to:
Posts (Atom)