Drove by today to check on the igloo, the last of the scaffold was removed today. The plaster guy was back sanding the kitchen ceiling and patching some holes.
The top floor has been sanded and the tilers was backing putting some tiles on the laundry area.
I notice a leak at the bottom toilet, site supervisor is sending the plumbers to have a look.
Our pictorial journey as we tackle the excitements and obstacles of building our Cosy Igloo
Thursday, January 27, 2011
Monday, January 24, 2011
Bathroom accessories & Skirtings and internal door handles
All the bathroom accessories are installed on the weekend. All internal door handles was installed today. Also all skirtings was fixed today as well since some of them was damaged due to the mini flood because someone left a window open and it rained !!
Thursday, January 20, 2011
Electrical all done
Internal electrical is all done.....power points, light switches and light batten is all installed today.
Kitchen ceiling needs to be fixed and repainted.
Kitchen ceiling needs to be fixed and repainted.
Wednesday, January 19, 2011
Aircon Vents, Bathrooms Plumbing, Balcony Railings
There is plenty of activity today at the Igloo. Aircon vents are installed and the balcony rails are also installed. The plumbers are installing the internal taps/loo/bathtube/vanity and also the external down pipes. There was also a little internal flood because a window was left open, not happy about that !!!
Monday, January 17, 2011
Bench Top Joints
There are no activity at the Igloo for a few days now...waiting for carpenters to get back from holidays.
We are having the "Butt ? " joint on our kitchen bench top not the Miter joint as shown at the display home. Below are pics of the miter joint which you can see holes start to form at the joints.
We are having the "Butt ? " joint on our kitchen bench top not the Miter joint as shown at the display home. Below are pics of the miter joint which you can see holes start to form at the joints.
Friday, January 7, 2011
Painting complete
7th Jan 2011 - The painters have finished, will give site supervisor a call on Monday to see what happens next.
Wednesday, January 5, 2011
Man Hole (Service Hole)
Alot of people put the man hole in the walk in robe? So every time a tradie goes to the roof cavity to fix something your cloths will be all dirty...etc. So we moved ours into the bathroom....plenty of room to put a ladder.
Painters have started
23nd Dec 2010 - the painters started just before christmas and should be complete by the 7th Jan 2011.