Friday, August 20, 2010

Bricks - more ice bricks + scaffolding

The scaffolding was completed on Thursday 19th August 2010. The plumbers also turned up in the arvo to do some more work on the 2nd level.
More bricks arrived this morning, hopefully the brickies will start next week.....

update - this arvo all the bricks was moved inside the fence :) lucky they did that or on Monday most of it will not be there...

Monday, August 16, 2010

Bricks - ground level complete

Woohooo, just talked to the brickies this morning, the ground level bricks will be completed today and the scaffolding will be put up this Thursday and the top story bricks will be layed....

Thursday, August 12, 2010

Bricks - front of igloo

The bricks are up at the front of four igloo. Abit more bricks to go around the garage and the scaffolding team with come and prep the whole house before the brick layer comes back to start the 2nd story.

Thursday, August 5, 2010

Bricks & Pipes

Thursday 5th August 2010 - I though it is time to take some pics of the gas and water pipes locations before the bricks go up and cover it all. Just for future reference so i know where all the pipes are. I did the same thing with all the drain pipes underground

Gas + Water pipes


A one man brickie...he is doing the whole house...which i think is awesome


The back alfresco is taking shape

Wednesday, August 4, 2010

Brick Layers have started

Monday 2nd August 2010 - Last week our site supervisor said there was a shortage of brick layers and the wait will be at least 4 weeks :( However on Monday he said he found a brickie that can start on our Igloo...very happy :-)
Looking good - the alfresco area, you can see the drain for the outdoor sink